Keep a volume record before choosing the order unit
A stockpile order, rectangular fill and concrete box all start with three measured dimensions. Add separate sections for changes in footprint or depth. This calculator reports geometry without choosing a material or allowance.
Worked example: main fill and side section
A 12 × 9 ft main section and a 6 × 3 ft side section, each 6 in deep, contain 54 + 9 = 63 ft³. Divide once by 27 for 2⅓ yd³, equivalent to 1.783961335296 m³. The 6 in depth is illustrative.
Continue with the material you selected
Use Gravel to estimate weight from a supplier density, Concrete Slab for thickness zones and labeled concrete yields, or Paver for a selected patio system and separate base layers. Aggregate Ordering handles supplier minimums, increments and delivery. A cubic-yard result alone is not a complete order.
Why do inches need conversion?
Length and width in feet need depth in feet too: 6 in ÷ 12 = 0.5 ft. Multiplying feet by feet by inches without conversion overstates cubic feet twelvefold.
Version 1.0.0 uses unrounded intermediate arithmetic and displays up to four decimal places. Measurements can be saved locally in Planner and handed off explicitly. Supplier rounding and piece-layout rules belong in the downstream material calculator.